ResourcesCapacity13 September 20266 min read

Working out whether the quarter actually fits

Most over-commitment is arithmetic you can do in week one. Subtract on-call and leave from the days a team has, then compare.

Almost every over-committed quarter was over-committed on the day it was planned, and the arithmetic that would have shown it takes about ten minutes. It does not get done because the numbers involved are slightly embarrassing: a six-person team has far fewer usable days than six people suggests, and writing that down makes the plan look worse.

The plan is not made worse by writing it down. It is made worse by discovering it in week eleven.

Do the arithmetic

Here is a six-person engineering team in a normal quarter, with 62 working days (a quarter after public holidays), six weeks of on-call between them, 24 days of booked leave, and 230 days already assigned to objectives.

StepDays
6 people x 62 working days372
less 6 weeks on call-30
less booked leave-24
less 15% interrupts-48
Real capacity270
Assigned to objectives230
Headroom40

Forty days of headroom looks comfortable. Headroom is not slack, though: it is the room the quarter needs for the work nobody has thought of yet.

Now change only the number people argue about. Put interrupts at 30% instead of 15% and real capacity drops to about 223 days, so the same 230-day plan is 7 days over. Nothing about the plan changed; the honest interrupt rate did. That is visible in week one and invisible in week eleven, which is the entire argument for counting it.

What has to come out

Gross headcount days are not capacity, and the gap between the two is where plans die.

  • On-call. A week on call is not a week on the objective somebody assigned you. Teams running a real rota lose five to ten per cent of the quarter to it before anything else.
  • Booked leave. The easy one, and the one most plans already include.
  • Interrupts and unplanned absence. Support escalations, the incident nobody scheduled, illness. This is the number that separates a plan from a wish, and your own history is the only useful source for it.
  • Onboarding. Somebody who joins in month two is not half a person for the quarter; they are closer to a quarter of one, and they cost a mentor time.

The number to argue about. If your team has never measured its interrupt load, start at 20% and watch what happens. Teams are usually indignant about that figure for one quarter and then quietly revise it upwards.

Lakshaya does the same subtraction per person rather than per team. Each person's days for objectives are their available days, less planned leave, less the team's on-call share and average unplanned leave, multiplied by a productivity factor (which you can leave at 100%). The team's figure is the sum of its people.

Why this belongs in a spreadsheet

Lakshaya takes capacity from a sheet rather than asking people to type it into a form, and that is a deliberate choice rather than a missing feature.

  • The sheet already exists. Every engineering organisation has one. Asking people to abandon a tool they are fluent in for a worse editor is how a capacity feature goes unused.
  • Spreadsheets are better at what-if. Reshuffling a quarter is spreadsheet work. The product is for the answer, not for the argument that produced it.
  • One generated template per team, per cycle, with the columns fixed and dropdowns for the team and the objective, so a sync cannot silently mean something different for two teams and nobody invents a column layout the import has to guess at.
  • Syncs happen when somebody asks for one. Nothing changes in the background. A sync replaces that team's capacity with what the sheet says right now, so sync a finished sheet rather than a half-filled one, and it reports any row it could not read (an unknown team, an objective name that matches nothing or matches two) instead of guessing.

The conversation it starts

The output is not a verdict on a team. It is arithmetic about a plan, held while there is still a quarter left in which to change it, and the three questions it answers are the three that get asked in week eleven anyway.

  • Does this fit? Assigned days against available days, with the overage named rather than implied.
  • Who is carrying it? An over-committed team is usually two over-committed people. The per-person view is the one that changes behaviour.
  • What gives? Objectives ranked by the days they consume, so the thing you drop is chosen rather than being whatever quietly slips.

A team that finishes the quarter having done four of five things it chose is in better shape than one that half-finished seven. The arithmetic is how you get to choose which.

The product tours show a capacity sheet syncing into a team's plan.

Key takeaways

  • Gross headcount days are not capacity. Subtract on-call, leave and a realistic interrupt rate before comparing anything to a plan.
  • Start your interrupt estimate at 20% if you have never measured it. Most teams revise upwards, not down.
  • Keep the planning in the spreadsheet your team already uses and sync the answer. A capacity form nobody fills in tells you nothing.